The Impact of Good and Bad Multitasking on Buffer Requirements of CCPM Portfolios

Authors

  • Mahdi Ghaffari University of Manchester United Kingdom
  • Margaret W Emsley University of Manchester United Kingdom

Keywords:

Critical Chain, Goldratt, Project Scheduling, Project Management, Buffer sizing, Portfolio Resource Capacity, Multitasking

Abstract

In project planning, it is presumed that resources will be available to pick up their allocated tasks as planned while what happens in reality is rarely this simple. This discrepancy between planning and reality intensifies in Critical Chain Project Management (CCPM) portfolios where no level of multitasking is allowed. Regarding this, Ghaffari and Emsley (2016) determined the boundary between good and bad multitasking in CCPM portfolios with various resource capacities that showed some limited levels of multitasking could be beneficial to alleviate resource availability issues in such environments. In this paper, the authors aim to investigate how good and bad multitasking affect buffer requirements of CCPM portfolios with the same resource capacities considered in the above study. In a deductive approach, a hypothesis is developed and tested through experiments of ten portfolios with similar size and complexity levels, each one containing four projects with a different resource capacity, and comparing the results to their simulated counterparts obtained by the mentioned study. The results show that buffer requirements of portfolios with resource capacity of 130% and lower can be reduced through allowance of higher levels of multitasking. As a major contribution, a framework for buffer requirements of CCPM portfolios with different levels of multitasking and resource capacity is recommended.

Author Biographies

  • Mahdi Ghaffari, University of Manchester United Kingdom

    Mahdi Ghaffari is a PhD candidate at The University of Manchester undertaking his research on resource availability issues in Critical Chain Multi-Project Management and their effects on sizes of buffers in such environments. He has achieved a Bachelors degree (BSc) in Industrial Engineering and Master of Science in Management of Projects. His experience includes working as a project manager of maintenance projects for about three years. He is also certified as PRINCE2 Practitioner by OGC based in the UK and PMP by PMI based in the USA.

  • Margaret W Emsley, University of Manchester United Kingdom

    Dr. Margaret Emsley is a civil and structural engineer who joined what was then UMIST in 1986, and she is now a Reader in the School of Mechanical, Aerospace and Civil Engineering in The University of Manchester. Previously she had carried out research at Loughborough University and worked as an engineer for Tarmac Construction. She was involved in setting up the MSc in Construction Project Management in 1987 and has contributed to the teaching of many courses at both undergraduate and postgraduate level. She has supervised 13 PhD students and over 150 MSc students and has 7 current PhD students. She is currently the Programme Director of the MSc Management of Projects Group of Programmes (which also includes Commercial Project Management, Construction Project Management and Engineering Project Management).

References

Demeulemeester, E., Vanhoucke, M. and Herroelen, W. (2003). RANGEN- A Random Network Generator for Activity-On-the-Node Networks. Journal of Scheduling. 6. 17-38.

Ghaffari, M. and Emsley, M. W. (2015). Current Status and Future Potential of the Research on Critical Chain Project Management. Surveys in Operations Research and Management Science. 20. 43-54.

Ghaffari, M. and Emsley, M. W. (2016). The Boundary Between Good and Bad Multitasking in CCPM. The Journal of Modern Project Management. 4 (1). 104-111.

Goldratt, E. M. (1997). Critical Chain. New York: North River Press.

Herroelen, W. and Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management. 19, 559-577.

Leach, L. P. (1999). Critical Chain Project Management Improves Project Performance. Project Management Journal. 30(2). 39-51.

Leach, L. P. (2000). Critical Chain Project Management. 2nd ed. Boston: Artech House.

Leach, L. P. (2003). Schedule and Cost Buffer Sizing: How to Account for the Bias Between Project Performance and Your Model. Project Management Journal. 34(2). 34-47.

Leach, L. P. (2005). Lean Project Management: 8 Principles for Success. Boise: Advanced Projects.

Leach, L. P. (2014). Critical Chain Project Management. 3rd ed. Boston: Artech House.

Lechler, T. G., Ronen, B. and Stohr, E. A. (2005). Critical Chain: A New Project Management Paradigm or Old Wine in New Bottles? Engineering Management Journal. 17, 45-58.

Matthews, B. and Ross, L. (2010). Research Methods: A Practical Guide ofr the Social Researchers. London: Pearson Education Limited.

Newbold, R. C. (1998). Project Management in The Fast Lane: applying the Theory of Constraints. London: St. Lucie Press.

Newbold, R.C. (2008). The Billion Dollar Solution. Lake Ridge, VA: ProChain Press.

Product Development Institute. (1999). A Tutorial On Critical Chain. [online].

Available From: http://materias.fi.uba.ar/7546/material/Tutorial_critical_chain.pdf [Accessed 16 April 2016].

Raz, T., Barnes, R. and Dvir, D. (2003). A Critical Look at Critical Chain Project Management. Project Management Journal. 34, 24-32.

Saunders, M., Lewis, P. and Thornhill, A. (2009). Research Methods for Business Students. 5th ed. London: Pearson Education Limited.

Steyn, H. (2001). An investigation into the fundamentals of critical chain project scheduling. International Journal of Project Management. 19, 363-369.

Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling. International Journal of Project Management. 20, 75-80.

Trietsch, D. (2005). Why A Critical Path by Any Other Name Would Smell Less Sweet? Project Management Journal. 36, 27-36.

Tukel, O. I., Rom, W. O. & Eksioglu, S. D. (2006). An investigation of buffer sizing techniques in critical chain scheduling. European Journal of Operational Research, 172, 401-416.

Downloads

Published

2022-05-20

How to Cite

The Impact of Good and Bad Multitasking on Buffer Requirements of CCPM Portfolios. (2022). The Journal of Modern Project Management, 4(2). https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/235

Similar Articles

1-10 of 459

You may also start an advanced similarity search for this article.