Assistance in selecting a project contracting strategy by combining complex systems theory and risk and vulnerability analysis

Authors

  • Julien Ventroux Université Paris-Saclay, FRANCE France
  • Franck Marle Ecole Centrale Paris Brazil
  • Ludovic Alexandre Vidal Université Paris-Saclay, FRANCE France

Keywords:

project management, contracting strategy, complex systems modelling, risk and vulnerability analysis, oil and gas projects

Abstract

Oil and gas development projects involve many contracts for engineering studies, item procurement, construction workforce, installation or commissioning. One key component of such projects is the definition of a contracting strategy, which consists of breaking the project down into work packages that will be awarded to contractors with specific remuneration and supervision modes. Indeed, it links global design with the local contracts and internal activities that must be undertaken to deliver the results. Risks are associated with every contract as well as with the interfaces between the client and contractor and between the contractors themselves. The problem is then to select an adequate contracting strategy, considering the risks that may occur before or after signing a contract, with direct and possibly indirect and higher impacts. This communication aims to present a method for analyzing the risks of such contracting strategies. The analysis focuses on technical and organizational interfaces, notably contractual ones that exist within these alternative strategies. The expected result is a risk analysis process and tool, which is included in the global project contracting strategy selection process. An industrial application in an international oil and gas company will be presented.

Author Biographies

  • Julien Ventroux, Université Paris-Saclay, FRANCE France

    Laboratoire Genie Industriel, CentraleSupélec,

  • Franck Marle, Ecole Centrale Paris Brazil

    Franck Marle is professor at Ecole Centrale Paris in the « Industrial Engineering » Laboratoryand « Enterprise Sciences » Department. Director ofa Chair with TOTAL about “Managing Procurement Risks in Complex Projects” for 2013. Habilitation to supervise research from Nantes University (2011):“An assistance to managing risks and vulnerabilities involved by complexity: application to planning and steering of complex and (thus) risky projects”. PhD in Engineering Sciences of Ecole Centrale Paris (2002): “Information model and methods to assist decision-making in project management”. Master of Sciencein Industrial Engineering of Ecole Centrale Lyon (1997).

  • Ludovic Alexandre Vidal, Université Paris-Saclay, FRANCE France

    Laboratoire Genie Industriel, CentraleSupélec

References

Abdul-Kadir, M. R., & Price, A. D. F. (1995). Conceptual phase of construction projects. International Journal of Project Management, 13(6), 387-393.

Adger, W. N. (2006). Vulnerability. Global environmental change, 16(3), 268-281

Ackermann, F., & Alexander, J. (2016). Researching complex projects: Using causal mapping to take a systems perspective. International Journal of Project Management, 34(6), 891-901.

Akinsiku, O. E., & Akinsulire, A. (2012). Stakeholders' perception of the causes and effects of construction delays on project delivery. Journal of Construction Engineering and Project Management, 2(4), 25-31.

Allison, E. H., Perry, A. L., Badjeck, M. C., Neil Adger, W., Brown, K., Conway, D & Dulvy, N. K. (2009). Vulnerability of national economies to the impacts of climate change on fisheries. Fish and fisheries, 10(2), 173-196.

Antoniou, F., Aretoulis, G. N., Konstantinidis, D., & Kalfakakou, G. P. (2013). Complexity in the evaluation of contract types employed for the construction of highway projects. Procedia-Social and Behavioral Sciences, 74, 448-458.

Arain, F.M., Low, S.P., (2006). Developers' views of potential causes of variation orders for institutional buildings in Singapore. Archit. Sci. Rev. 49 (1), 59–74.

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 387-407.

Bayraktar, M. E., & Hastak, M. (2009). A decision support system for selecting the optimal contracting strategy in highway work zone projects. Automation in Construction, 18(6), 834-843.

Bernard, F., Salviac, E., & Bernard, F. (2009). Fonction achats: controle interne et gestion des risques. Editions Maxima.

Chan, E. H., & Ann, T. W. (2005). Contract strategy for design management in the design and build system. International journal of project management, 23(8), 630-639.

Chapman, C., & Ward, S. (1996). Project risk management: processes, techniques and insights. John Wiley.

Chapman, R. J. (1998). The role of system dynamics in understanding the impact of changes to key project personnel on design production within construction projects. International Journal of Project Management, 16(4), 235-247.

Cheng, E. W., & Li, H. (2004). Contractor selection using the analytic network process. Construction management and Economics, 22(10), 1021-1032.

Chiang, F. Y., Vincent, F. Y., & Luarn, P. (2017). Construction Contractor Selection in Taiwan Using AHP. International Journal of Engineering and Technology, 9(3).

Chung, K. S. K., & Crawford, L. (2016). The Role of Social Networks Theory and Methodology for Project Stakeholder Management. Procedia-Social and Behavioral Sciences, 226, 372-380.

Clivillé, V. (2004). Approche systémique et méthode multicritère pour la définition d'un système d'indicateurs de performance (Doctoral dissertation, Chambéry).

Cook, E. L., & Hancher, D. E. (1990). Partnering: contracting for the future. Journal of Management in Engineering, 6(4), 431-446.

Cooper, D.F., Grey. S., Raymond. G and WalkerGopal. P., (2005). Project Risk Management Guidelines. John Wiley & Sons Ltd.

Corvellec, H. (2009). The practice of risk management: Silence is not absence. Risk Management, 11(3-4), 285-304.

Davis, K. (2014). Different stakeholder groups and their perceptions of project success. International Journal of Project Management, 32(2), 189-201.

Davies, A., & Brady, T. (2016). Explicating the dynamics of project capabilities. International Journal of Project Management, 34(2), 314-327.

De Rosnay, J. (1975). Le macrocosme: vers une vision globale. Éditions du Seuil.

Dey, P. K. (2001). Decision support system for risk management: a case study. Management Decision, 39(8), 634-649.

Donnadieu, G., Durand, D., Neel, D., Nunez, E., & Saint-Paul, L. (2003). L’Approche systémique: de quoi s’agit-il. Union Européenne de Systémique.

Ennaouri, I. (2010). Modélisation de la dégradation hydraulique et structurale des réseaux sanitaires et pluviaux (Doctoral dissertation, École Polytechnique de Montréal).

Eppinger, S. D., & Browning, T. R., (2012). Design structure matrix methods and applications. MIT press.

Fong, P. S. W., & Choi, S. K. Y. (2000). Final contractor selection using the analytical hierarchy process. Construction Management & Economics, 18(5), 547-557.

Furstenberg, G. M. (1969). Default risk on FHA-insured home mortgages as a function of the terms of financing: a quantitative analysis. The Journal of Finance, 24(3), 459-477.

Griffiths, F. (1989). Project contract strategy for 1992 and beyond. International Journal of Project Management, 7(2), 69-83.

Guitouni, A., & Martel, J. M. (1998). Tentative guidelines to help choosing an appropriate MCDA method. European Journal of Operational Research, 109(2), 501-521.

Hartman, F., & Snelgrove, P. (1996). Risk allocation in lump-sum contracts—Concept of latent dispute. Journal of construction engineering and management, 122(3), 291-296.

Holt, G. D. (1998). Which contractor selection methodology?. International Journal of project management, 16(3), 153-164.

Howard, W.E., Bell, L.C., & McCormick, R.E. (1997). Economic principales of contractor compensation. Journal of Management in Engineering, 13(5), 81-89.

Jefferies, A. T., Desalos, A. P., & Van Der Linden, C. (2004, January). Matterhorn export pipeline and steel catenary riser design, fabrication, and installation. In Offshore Technology Conference. Offshore Technology Conference.

Jin, Y., & Jorion, P. (2006). Firm value and hedging: Evidence from US oil and gas producers. The Journal of Finance, 61(2), 893-919.

Jin, L., & Robey, D. (2008). Bridging social and technical interfaces in organizations: An interpretive analysis of time-space distanciation. Information and Organization, 18(3), 177-204.

Larson, E.W., & Gray, C.F. (2010). Project management: the managerial process. McGraw-Hill Education-Europe, Fifth edition.

Le Moigne, J. L. (1990). La modélisation des systèmes complexes. Paris: Bordas, Dunot, 1990.

Le Moigne, J. L. (1994). La théorie du système général: théorie de la modélisation. jeanlouis le moigne-ae mcx.

Lin, C. H., Tung, C. M., & Huang, C. T. (2006). Elucidating the industrial cluster effect from a system dynamics perspective. Technovation, 26(4), 473-482.

Maders, H. P., & Masselin, J. L. (2009). Piloter les risques d'un projet. Editions Eyrolles.

Marle, F., & Vidal, L. (2008). Potential applications of DSM principles in project risk management. In DSM 2008: Proceedings of the 10th International DSM Conference, Stockholm, Sweden, 11.-12.11. 2008.

Marle, F., Vidal, L. A., & Bocquet, J. C. (2013). Interactions-based risk clustering methodologies and algorithms for complex project management. International Journal of Production Economics, 142(2), 225-234.

Maystre, L. Y., Pictet, J., & Simos, J. (1994). Méthodes multicritères ELECTRE: description, conseils pratiques et cas d'application à la gestion environnementale (Vol. 8). PPUR presses polytechniques.

Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, 33(2), 446-457.

Nasirzadeh, F., & Nojedehi, P. (2013). Dynamic modeling of labor productivity in construction projects. International Journal of Project Management, 31(6), 903-911.

Nasirzadeh, F., Khanzadi, M., & Rezaie, M. (2014). Dynamic modeling of the quantitative risk allocation in construction projects. International Journal of Project Management, 32(3), 442-451.

Olsen, B. E., Haugland, S. A., Karlsen, E., & Husøy, G. J. (2005). Governance of complex procurements in the oil and gas industry. Journal of Purchasing and Supply management, 11(1), 1-13.

Patrucco, P. P. (2002). Review article: social and contractual interactions in the production of technological knowledge. Information Economics and Policy, 14(3), 405-416.

Petit, P. (2008). Toute la fonction achats: savoirs, savoir-faire, savoir-être. Dunod.

Pfeffer, D. J. (2010). The construction contract: Lump sum vs. cost plus. The New York Law Journal, 11-13.

Posner, E. A. (2003). Economic analysis of contract law after three decades: Success or failure?. The Yale Law Journal, 112(4), 829-880.

Ramsay, J., & Wilson, I. (1990). Sourcing/contracting strategy selection. International Journal of Operations & Production Management, 10(8), 19-28.

Rodrigues, A., & Bowers, J. (1996). The role of system dynamics in project management. International Journal of Project Management, 14(4), 213-220.

Rouvière, F. (2010). La remise en cause du contrat par le juge. L’éfficacité du contrat. Aix-en-Provence, France. Dalloz, p.41-56.

Sterman, J. D. (2001). System dynamics modeling: tools for learning in a complex world. California management review, 43(4), 8-25.

Steward, D. V. (1981). The design structure system: A method for managing the design of complex systems. Engineering Management, IEEE Transactions on, (3), 71-74.

Thompson, J. D. (1967). Organizations in action: Social science bases of administrative theory. Transaction publishers.

Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International journal of project management, 19(8), 457-464.

Ventroux, J., (2016), Aide à la maîtrise des risques liés à la contractualisation et l’exécution d’un projet complexe pétrolier (Doctoral dissertation, Ecole CentraleSupelec).

Vidal, L. A. (2009). Thinking project management in the age of complexity. Particular implications on project risk management (Doctoral dissertation, Ecole Centrale Paris).

Wang, L., Kunc, M., & Bai, S. J. (2017). Realizing value from project implementation under uncertainty: An exploratory study using system dynamics. International Journal of Project Management, 35(3), 341-352.

Watt, D. J., Kayis, B., & Willey, K. (2010). The relative importance of tender evaluation and contractor selection criteria. International Journal of Project Management, 28(1), 51-60.

Williamson, O. E. (1988). The logic of economic organization. Journal of Law, Economics, & Organization, 4(1), 65-93.

Yang, Q., Lu, T., Yao, T., & Zhang, B. (2014). The impact of uncertainty and ambiguity related to iteration and overlapping on schedule of product development projects. International Journal of Project Management, 32(5), 827-837.

Yang, R. J., Zou, P. X., & Wang, J. (2016). Modelling stakeholder-associated risk networks in green building projects. International journal of project management, 34(1), 66-81.

Zaghloul, R., & Hartman, F. (2003). Construction contracts: the cost of mistrust. International Journal of Project Management, 21(6), 419-424.

Zhang, H. (2007). A redefinition of the project risk process: Using vulnerability to open up the event-consequence link. International journal of project management, 25(7), 694-701.

Downloads

Published

2022-05-20