Combining EDM and EVM: a proposed simplification for project time and cost management
Keywords:
Earned value, Earned schedule, Earned duration, Cost forecasting, Duration forecasting, Project management effort, Techniques combinationAbstract
Earned value management (EVM), a technique mainly used to manage project cost, was developed during the second half of the twentieth century by an agency of the USA government. It was enriched, at the beginning of the current century, with an extension named earned schedule (ES) (Lipke, 2003), which added to EVM the capability to manage the project schedule.In 2014, earned duration management (EDM), a novel, and monetary value free technique for project schedule management, was proposed by Khamooshi and Golafshani (2014). Earned duration (ED), the project schedule indicator from EDM uses only activity dates and durations from EVM, and aims at replacing ES. By not using cost as a proxy for time, ED overcomes one of the most criticized aspect of ES.This paper intends to (i) compare ED with ES to learn some fundamental lessons, (ii) propose the combination of ED and planned value (PV) from EVM to produce an EDM-based project-level earned value (EV〗^d), and (iii) assess the adequacy of 〖EV〗^d as an alternative to earned value (EV) from EVM in project time and cost management. The comparison between the project real cost and both EVM and EDM-based independent estimates at completion, on a set of real projects, was the vehicle for assessing the adequacy of 〖EV〗^d as a viable alternative to EV.Workload avoidance by replacing activities earned value calculations with the simpler and more consistent determination of the activities earned durations, and the enhanced visibility of potential schedule problems caused by lower cost/duration ratio activities, are benefits that 〖EV〗_d offers to project managers.
References
Andrade, P., Batselier, J., Salvaterra, F., and Vanhoucke, M., 2015. Introduction to Earned Duration. The Measurable News, 2:15-27
Batselier, J., and Vanhoucke, M., 2014. Real project data. http://www.projectmanagement.ugent.be/research/data/realdata.
Batselier, J., Vanhoucke, M., 2015a. Construction and evaluation framework for a real-life project database. Int. J. Proj. Manag. 33, 697–710.
Batselier, J., and Vanhoucke, M., 2015b. Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management. International Journal of Project Management, 33:1588–1596.
Colin, J., and Vanhoucke, M., 2015. Comparison of the performance of various project control methods using earned value management systems. Expert Systems with Applications, 42:3159–3175.
Fleming, Q. W., & Koppelman, J. M., 2004. If EVM is so good, why isn't it used on all projects? The Measurable News, 2004.
Khamooshi, H., 2014. EDM: Earned Duration Management a Novel Approach - Webinar. https://www.projectmanagement.com/videos/289128/EDM--Earned-Duration-Management-a-Novel-Approach.
Khamooshi, H., and Golafshani, H., 2014. EDM: Earned Duration Management, a new approach to schedule performance management and measurement. International Journal of Project Management, 32:1019–1041.
Khamooshi, H., and Abdi, A., 2016. Project Duration Forecasting Using Earned Duration Management with Exponential Smoothing Techniques. J. Manage. Eng., 04016032.
Lipke, W., 2003. Schedule is Different. The Measurable News, March, pp. 10-15.
Lipke, W. H., 2009. Earned schedule: an extension to earned value management for managing schedule performance. 1st ed. [e-book] Retrieved from: http://www.amazon.com.
Lipke, W., 2012. Speculations on project duration forecasting. The Measurable News, 3:3–7.
Lipke, W., Zwikael, O., Henderson, K., and Anbari, F., 2009. Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27:400–407.
Lukas, J., 2008. Earned Value Analysis – Why it Doesn't Work, AACE International Transactions, EVM.01. 2. http://www.icoste.org/LukasPaper.pdf.
PMI, 2011. Practice Standard for Earned Value Management (2nd ed.). Newtown Square: Project Management Institute, Inc.
Vandevoorde, S. and Vanhoucke, M., 2006. A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24:289–302.
Vanhoucke, M. and Vandevoorde, S., 2007. A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58:1361–1374.
Vanhoucke, M., 2010a. Measuring time – improving project performance using earned value management. International series in operations research and management science (Vol. 136). Springer.
Vanhoucke, M., 2010b. Using activity sensitivity and network topology information to monitor project time performance. Omega The International Journal of Management Science, 38:359–370.
Vanhoucke, M., 2011. On the dynamic use of project performance and schedule risk information during project tracking. Omega The International Journal of Management Science, 39:416–426.
Vanhoucke, M., 2012. Measuring the efficiency of project control using fictitious and empirical project data. International Journal of Project Management, 30:252–263.
Vanhoucke, M. 2014. Integrated project management and control: First come the theory, then the practice. In Management for professionals. Springer.
Downloads
Published
Issue
Section
License
Copyright (c) 2022 Mario Vanhoucke, Paulo André Andrade

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.