Combining EDM and EVM: a proposed simplification for project time and cost management

Authors

  • Mario Vanhoucke Faculty of Economics and Business Administration, Ghent University; Belgium Technology and Operations Management Area, Vlerick Business School, Ghent, Belgium; University College London, United Kingdom Belgium
  • Paulo André Andrade Techisa do Brasil Ltda. ITA electronic engineer; over 25 years’ experience in projects at the IBM and R&D projects.

Keywords:

Earned value, Earned schedule, Earned duration, Cost forecasting, Duration forecasting, Project management effort, Techniques combination

Abstract

Earned value management (EVM), a technique mainly used to manage project cost, was developed during the second half of the twentieth century by an agency of the USA government. It was enriched, at the beginning of the current century, with an extension named earned schedule (ES) (Lipke, 2003), which added to EVM the capability to manage the project schedule.In 2014, earned duration management (EDM), a novel, and monetary value free technique for project schedule management, was proposed by Khamooshi and Golafshani (2014). Earned duration (ED), the project schedule indicator from EDM uses only activity dates and durations from EVM, and aims at replacing ES. By not using cost as a proxy for time, ED overcomes one of the most criticized aspect of ES.This paper intends to (i) compare ED with ES to learn some fundamental lessons, (ii) propose the combination of ED and planned value (PV) from EVM to produce an EDM-based project-level earned value (EV〗^d), and (iii) assess the adequacy of 〖EV〗^d as an alternative to earned value (EV) from EVM in project time and cost management. The comparison between the project real cost and both EVM and EDM-based independent estimates at completion, on a set of real projects, was the vehicle for assessing the adequacy of 〖EV〗^d as a viable alternative to EV.Workload avoidance by replacing activities earned value calculations with the simpler and more consistent determination of the activities earned durations, and the enhanced visibility of potential schedule problems caused by lower cost/duration ratio activities, are benefits that 〖EV〗_d offers to project managers.

Author Biography

  • Mario Vanhoucke, Faculty of Economics and Business Administration, Ghent University; Belgium Technology and Operations Management Area, Vlerick Business School, Ghent, Belgium; University College London, United Kingdom Belgium

    Biography Prof. Dr. Mario Vanhoucke is professor at the Ghent University and head of the department of Information Science and Operations Management. He is also part-time professor at Vlerick Leuven Gent Management School (Belgium) and University College of London (UK). He teaches Project Management, Business Statistics and Applied Operations Research. Read more. Teaching Mario teaches “Project Management” in the MSc course module CEGEG041 at University College of London (UK) and Ghent University (Belgium). He also teaches “Decision Sciences” and “Business Statistics” at Vlerick Leuven Gent Management School (Belgium) and Beijing University (China), “Applied Operations Research” at Ghent University (Belgium), and Read more. Research Mario‘s research interests include project management, project risk management and project control (Earned Value Management) as well as health-care optimisation and machine scheduling. Here you can see some of his recent research projects. http://www.ucl.ac.uk/msi/profile/mario-vanhoucke/research Publications “New computational results for the discrete time/cost trade-off problem in project networks”, Journal of the Operational Research Society, 1998, 49 (11), 1153-1163 (with E. Demeulemeester, B. Foubert, W. Herroelen and M. Vanhoucke). “An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem”, Annals of Operations Research, 2001, 102, 179-196 (with E. Demeulemeester and W. Herroelen). “On maximizing the net present value of a project under renewable resource constraints”, Management Science, 2001, 47, 1113-1121 (with E. Demeulemeester and W. Herroelen). "Scheduling projects with linearly time-dependent cash flows to maximize the net present value", International Journal of Production Research, 2001, 39, 3159-3181 (with E. Demeulemeester and W. Herroelen). “Discrete time/cost trade-offs in project scheduling with time-switch constraints”, Journal of the Operational Research Society, 2002, 53, 741-751 (with E. Demeulemeester and W. Herroelen). “A random network generator for activity-on-the-node networks”, Journal of Scheduling, 2003, 6, 13-34 (with E. Demeulemeester and W. Herroelen). “Progress payments in project scheduling problems”, European Journal of Operational Research, 2003, 148, 604-620 (with E. Demeulemeester and W. Herroelen). “New computational results for the discrete time/cost trade-off problem with time-switch constraints”, European Journal of Operational Research, 2005, 165, 359-374. “A bi-population based genetic algorithm for the RCPSP”, Lecture Notes in Computer Science, 2005, 3483, 378-387 (with D. Debels). “A hybrid scatter search/electromagnetism meta-heuristic for project scheduling”, European Journal of Operational Research, 2006, 169, 638-653 (with D. Debels, B. De Reyck, and R. Leus). “Work continuity constraints in project scheduling”, Journal of Construction Engineering and Management, 2006, 132, 14-25. “A simulation and evaluation of earned value metrics to forecast the project duration”, Journal of the Operational Research Society, 2007, 58, 1361–1374 (with S. Vandevoorde). “A decomposition-based genetic algorithm for the resource-constrained project scheduling problem”, Operations Research, 2007, 55, 457-469 (with D. Debels). “An electromagnetism meta-heuristic for the nurse scheduling problem”, Journal of Heuristics, 2007, 13, 359-385 (with B. Maenhout). “A simulation analysis of errors in the design of costing systems”, The Accounting Review, 2007, 82, 939-962 (with E. Labro). “The discrete time/cost trade-off problem: extensions and heuristic procedures”, Journal of Scheduling, 2007, 10, 311-326 (with D. Debels). “A comparison and hybridization of crossover operators for the nurse scheduling problem”, Annals of Operations Research, 2008, 159, 333 – 353 (with B. Maenhout). “An evaluation of the adequacy of project network generators with systematically sampled networks”, European Journal of Operational Research, 2008, 187, 511–524 (with J. Coelho, D. Debels, B. Maenhout and L. Tavares). “The impact of various activity assumptions on the lead-time and resource utilization of resource-constrained projects”, Computers and Industrial Engineering, 2008, 54, 140–154 (with D. Debels). “Setup times and fast tracking in resource-constrained project scheduling”, Computers and Industrial Engineering, 2008, 54, 1062-1070. “Diversity in resource consumption patterns and costing system robustness to errors”, Management Science, 2008, 54, 1715 – 1730 (with E. Labro). “On the characterisation and generation of nurse scheduling problem instances”, European Journal of Operational Research, 2009, 196, 457–467 (with B. Maenhout). “The impact of incorporating nurse-specific characteristics in a cyclical scheduling approach”, Journal of the Operational Research Society, 2009, 60, 1683-1698 (with B. Maenhout). “A finite capacity production scheduling procedure for a Belgian steel company”, International Journal of Production Research, 2009, 47, 561 – 584 (with D. Debels). “A scatter search heuristic for maximizing the net present value of a resource-constrained project with fixed activity cash flows”, International Journal of Production Research, 2010, 48, 1983-2001. “A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem”, European Journal of Operational Research, 2010, 201, 409-418 (with V. Van Peteghem). “Using activity sensitivity and network topology information to monitor project time performance”, Omega - International Journal of Management Science, 2010, 38, 359-370. “Introducing optimization techniques to students: An exam case distribution model”, INFORMS Transactions on Education, 2010, 206, 155-167. “A hybrid scatter search heuristic for personalized crew rostering in the airline industry”, European Journal of Operational Research, 2010, 206, 155-167 (with B. Maenhout). “Branching strategies in a branch-and-price approach for a multiple objective nurse scheduling problem”, Journal of Scheduling, 2010, 13, 77-93 (with B. Maenhout). “On the dynamic use of project performance and schedule risk information during project tracking”, Omega - International Journal of Management Science, 2011, 39, 416-426. “Using resource scarceness characteristics to solve the multi-mode resource-constrained project scheduling problem”, Journal of Heuristics, 2011, To appear (with V. Van Peteghem) “An evolutionary approach for the nurse rerostering problem”, Computers and Operations Research, 2011, 38, 1400-1411 (with B. Maenhout). “Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers”, European Journal of Operational Research, 2011, to appear (with J. Coelho) “On maximizing the net present value of a project under renewable resource constraints”, Management Science. “A decomposition-based genetic algorithm for the resource-constrained project scheduling problem”, Operations Research. “On maximizing the net present value of a project under renewable resource constraints”, Management Science, 2001, 47, 1113-1121 (with E. Demeulemeester, E. and W. Herroelen). “A simulation analysis of errors in the design of costing systems”, The Accounting Review, 2007, 82, 939-962 (with E. Labro). “A decomposition-based genetic algorithm for the resource-constrained project scheduling problem”, Operations Research, 2007, 55, 457-469 (with D. Debels). “Diversity in resource consumption patterns and costing system robustness to errors”, Management Science, 2008, 54, 1715 – 1730 (with E. Labro).

References

Andrade, P., Batselier, J., Salvaterra, F., and Vanhoucke, M., 2015. Introduction to Earned Duration. The Measurable News, 2:15-27

Batselier, J., and Vanhoucke, M., 2014. Real project data. http://www.projectmanagement.ugent.be/research/data/realdata.

Batselier, J., Vanhoucke, M., 2015a. Construction and evaluation framework for a real-life project database. Int. J. Proj. Manag. 33, 697–710.

Batselier, J., and Vanhoucke, M., 2015b. Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management. International Journal of Project Management, 33:1588–1596.

Colin, J., and Vanhoucke, M., 2015. Comparison of the performance of various project control methods using earned value management systems. Expert Systems with Applications, 42:3159–3175.

Fleming, Q. W., & Koppelman, J. M., 2004. If EVM is so good, why isn't it used on all projects? The Measurable News, 2004.

Khamooshi, H., 2014. EDM: Earned Duration Management a Novel Approach - Webinar. https://www.projectmanagement.com/videos/289128/EDM--Earned-Duration-Management-a-Novel-Approach.

Khamooshi, H., and Golafshani, H., 2014. EDM: Earned Duration Management, a new approach to schedule performance management and measurement. International Journal of Project Management, 32:1019–1041.

Khamooshi, H., and Abdi, A., 2016. Project Duration Forecasting Using Earned Duration Management with Exponential Smoothing Techniques. J. Manage. Eng., 04016032.

Lipke, W., 2003. Schedule is Different. The Measurable News, March, pp. 10-15.

Lipke, W. H., 2009. Earned schedule: an extension to earned value management for managing schedule performance. 1st ed. [e-book] Retrieved from: http://www.amazon.com.

Lipke, W., 2012. Speculations on project duration forecasting. The Measurable News, 3:3–7.

Lipke, W., Zwikael, O., Henderson, K., and Anbari, F., 2009. Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27:400–407.

Lukas, J., 2008. Earned Value Analysis – Why it Doesn't Work, AACE International Transactions, EVM.01. 2. http://www.icoste.org/LukasPaper.pdf.

PMI, 2011. Practice Standard for Earned Value Management (2nd ed.). Newtown Square: Project Management Institute, Inc.

Vandevoorde, S. and Vanhoucke, M., 2006. A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24:289–302.

Vanhoucke, M. and Vandevoorde, S., 2007. A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58:1361–1374.

Vanhoucke, M., 2010a. Measuring time – improving project performance using earned value management. International series in operations research and management science (Vol. 136). Springer.

Vanhoucke, M., 2010b. Using activity sensitivity and network topology information to monitor project time performance. Omega The International Journal of Management Science, 38:359–370.

Vanhoucke, M., 2011. On the dynamic use of project performance and schedule risk information during project tracking. Omega The International Journal of Management Science, 39:416–426.

Vanhoucke, M., 2012. Measuring the efficiency of project control using fictitious and empirical project data. International Journal of Project Management, 30:252–263.

Vanhoucke, M. 2014. Integrated project management and control: First come the theory, then the practice. In Management for professionals. Springer.

Downloads

Published

2022-05-20

How to Cite

Combining EDM and EVM: a proposed simplification for project time and cost management. (2022). The Journal of Modern Project Management, 5(2). https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM01411