Merging PDM, RSM and LSM - Scheduling Approaches into a Single Construction Project Scheduling System

Authors

  • Pierre Bonnal CERN Switzerland Switzerland
  • Mathieu Baudin Product design and Innovation Laboratory, ENSAM ParisTech, Paris, France
  • Jurgen De Jonghe CERN, Geneva, Switzerland

Keywords:

construction project scheduling, linear scheduling method (LSM), repetitive scheduling method (RSM), unified project scheduling system (UPSS)

Abstract

There are projects for which the classical Critical Path method (CPM) or Precedence Diagramming Method (PDM) scheduling techniques are not the most suitable. Several alternative approaches have been developed over the last two decades to cope with the scheduling requirements of construction projects that are made of either repetitive activities or activities that have a linear development. Construction projects, and more specifically large-scale construction endeavors, are often composed of a mixture of repetitive activities, linear activities and more conventional project activities. The approach that is proposed in the present article enables construction practitioners to consider these three types of activities in a unique scheduling model — called Unified Project Scheduling System (UPSS) — that has a level of complexity similar to the one of CPM or PDM. UPSS has been designed so that most of the resource-constrained project scheduling algorithms can be used.

Author Biographies

  • Pierre Bonnal, CERN Switzerland Switzerland

    Senior Project Engineer with the Office of the Director of Accelerators and Technology, involved in providing project management support and advices to projects (as from Sept. 2010) > Technical Coordinator for the PS Booster Upgrade Project > CERN's Scientist-in-charge for the PURESAFE Initial Training Network > Member of the CERN A&T Sector's Maintenance Management Initiative > Member of the CERN's Corporate Risk Management Initiative. Senior lecturer Université de Lausanne / HEC School of Business February 2007 – Present (6 years 4 months) Instructor of the "R&D Management" course (M.Sc. in Management program) Institut National Polytechnique de Toulouse Ph.D., Industrial Systems Management 1997 – 2001 Université Paul Cézanne (Aix-Marseille III) D.E.A., Industrial Project Management 1989 – 1990 Université du Québec à Trois-Rivières M.Sc., Project Management 1989 – 1990 Ecole centrale de Marseille M.Sc., Industrial Eng. 1988 – 1990 Ecole nationale d'Ingénieurs de Tarbes M.Sc., Mechanical Eng. 1983 – 1988 Interests: Project management and governance, Front-end project management (feasibility analyses), Project risk management, Quality management, Product Lifecycle Management (PLM), Innovation and R&D management and governance, Corporate strategy and governance.

  • Mathieu Baudin, Product design and Innovation Laboratory, ENSAM ParisTech, Paris, France

    Graduated in 2011 from the French Engineering school Centrale Marseille. This degree is equivalent to a masters degree in engineering. In 2011 as well, I graduated from the University Paul Cézanne, Aix-Marseille III in a masters degree in Theoretical Chemistry, and Analytical Chemistry for which I performed a six month master thesis at the University of Nottingham in translational medical imaging, with Prof. Thomas Meersmann.

    I am now performing my PhD at CERN, Geneva, Switzerland, in industrial engineering. My grad school is at Ecole Nationale Supérieure d'Arts et Métiers ParisTech (ENSAM ParisTech, Paris, France). I am working on intervention models suited to collaborative intervention planning and scheduling, and their optimization based on radiation protection data.

  • Jurgen De Jonghe, CERN, Geneva, Switzerland

    Holds a MSc in computer science and applied mathematics from the University of Leuven, Belgium. At CERN, he was in charge of all business processes and administrative workflow from 1992. Since 1999, he has been in charge of providing project management tools for internal use. These tools have been used in a variety of projects ranging from the ATLAS detector (the largest particle physics collaboration ever), the LHC accelerator, EGEE (the European grid project) and now for planning all strategic activities at CERN. Jurgen has over 15 years of experience leading a software development team for medium to large software development projects.

References

Arditi, D. ; Albulak, M. Z. (1986) “Line-of- balance scheduling in pavement con- struction.” J. Constr. Eng. Manage., ASCE, 112 (3) 411–424.

Arditi, D.; Psarros, M. K. (1987) “SYRUS — System for repetitive unit scheduling.” Proc. of the NORDNET/INTERNET/ PMI’87 Conf. on Project Management, Verkefnastjomun, the Icelandic Project Management Society, Reykjavik, Iceland.

Arditi, D.; Tokdemir, O. B.; Suh, K. (1999) “Effect of learning on line-of-balance scheduling.” Int. J. Proj. Manage., 15 (5) 265–277.

Ashley, D. B. (1980) “Simulation of repet- itive-unit construction.” J. Constr. Div., ASCE, 106 (2) 185–194.

Barrie, D. S. and Paulson, B. C. Jr. (1978) Professional Construction Management. N.-Y.: McGraw-Hill, pp. 232-233.

Birrell, G. S. (1980) “Construction Planning - Beyond the Critical Path.” J. Constr. Div., ASCE, 106 (CO3) 389-407.

Borcherding, J. D. (1989) Factors that have an adverse effect on productivity. Discus- sion Paper of Construction Operation, University of Texas at Austin, Austin, TX.

Carr, R. I.; Meyer, W. L. (1974) “Planning Construction of Repetitive Building Units.” J. Constr. Div., ASCE, 100 (CO3) 403-412.

Chrzanowski, E. N.; Johnston, D. W. (1986) “Application of Linear Scheduling.” J. Constr. Eng. Manage., ASCE, 112 (4) 476-491.

Construction Industry Cost Effectivenes Task Force (1980) “Scheduled Overtime

Effect on Construction Projects.” Report. The Business Roundtable, New York.

Dressler, J. (1980) “Construction Manage- ment in West Germany.” J. Constr. Div., ASCE, 106 (CO4) 447-487.

Eldin, N. N.; Senouci, A. B. (1994) “Sched- uling and control of linear projects.” Canadian Journal of Civil Engineering, 21 (2) 219–230.

Eldin, N. N.; Senouci, A. B. (2000) “Sched- uling of linear projects with single loop structures.” Advances in Engineering Software, 31. 803–814.

El-Rayes, K.; Moselhi, O. (1998) “Re- source-driven scheduling of repetitive activities.” Constr. Manage. Econom., 16 (4) 433–446.

El-Rayes, K.; Moselhi, O. (2001a) “Opti- mizing resource utilization for repetitive construction projects.” J. Constr. Eng. Manage., ASCE, 127 (1) 18–27.

El-Rayes, K. (2001b) “Object oriented model for repetitive construction scheduling.”

J. Constr. Eng. Manage., ASCE, 127 (3) 99–205.

El-Rayes, K.; Ramanathan, R.; Moselhi, O.

(2002) “An object-oriented model for planning and control of housing con- struction.” Constr. Manage. Econom., 20 (3) 201-210.

Gorman, J. E. (1972) “How to Get Visual Impact on Planning Diagrams,” Roads and Streets, 115 (8) 74-75.

Halpin, D. W.; Woodhead, R. W. (1976) Design of Construction Process Operations,

N.-Y.: John Wiley & Sons, 30-36.

Handa, V.; Barcia R. (1986) “Linear sched- uling using optimal control theory.” Journal of Construction Engineering and Management, ASCE, 112 (3), May/June 1986, pp. 387–393.

Harmelink, D. J. (2001) “Linear Scheduling Model: float characteristics.” J. Constr. Eng. Manage., ASCE, 127 (4) 255–260.

Harmelink, D. J.; Rowings, J. E. (1998) “Lin- ear scheduling model: Development of controlling activity path.” J. Constr. Eng. Manage., ASCE, 124 (4) 263–268.

Harris, F. C.; Evans, J. B. (1977) “Road Construction - Simulation Game for Site Managers.” J. Constr. Div., ASCE, 103 (CO3) 405-414.

Harris, R. B.; Ioannou, P. G. (1998) “Sched- uling Projects with Repeating Activities.” J. Constr. Eng. Manage., ASCE, 124 (4) 269-278.

Hartmann, S. (2001) Project scheduling under limited resources: models, methods and applications. Belin: Springer.

Hegazy, T.; Moselhi, O.; Fazio, P. (1993) “BAL: An algorithm for scheduling and control of linear projects.” AACE Trans- actions, Morgantown, WV, 8.1–8.14.

Johnston, D. W. (1981) “Linear Scheduling Method for Highway Construction.” J. Constr. Div., ASCE, 107 (CO2) 241-261.

Kavanagh, D. P. (1985) “SIREN: a repetitive construction simulation model.” J. Constr. Eng. Manage., ASCE, 111 (3) 308–323.

Leu, S.; Hwang, S. (2001) “Optimal repetitive scheduling model with shareable resource constraint.” J. Constr. Eng. Manage., ASCE, 127 (4) 270–280.

Lumsden, P. (1968) The line-of-balance method. Tarrytown, N.-Y.: Pergamon.

Lutz, J. D.; Halpin, D. W. (1992) “Analyzing linear construction operations using simulation and line-of-balance.” Proc. of the 71st Annual Meeting of the Trans- portation Research Board, Record 1351, National Academy Press, Washington, D.C., 48–56.

Lutz, J. D.; Halpin, D. W.; and Wilson, J. R.

(1994). “Simulation of learning develop- ment in repetitive construction.” J. Constr. Eng. Manage., ASCE, 120 (4) 753–773.

Moselhi, O.; El-Rayes, K. (1993) “Scheduling of repetitive projects with cost optimiza- tion.” J. Constr. Eng. Manage., ASCE, 119 (4) 681–697.

Moselhi, O.; Hassanein, A. (2003) “Opti- mized scheduling of linear projects.” J. Constr. Eng. Manage., ASCE, 129 (6) 664–673.

O’Brien, J. J. (ed.) (1969) Scheduling Hand-

O’Brien, J. J. (1975) “VPM Scheduling for High-Rise Buildings.” J. Constr. Div., ASCE, 101 (CO4) 895-905.

O’Brien, J. J.; Kreitzberg, F. C.; Mikes, F. W.

(1985) “Network scheduling variation for repetitive work.” J. Constr. Eng. Manage., ASCE, 111 (2) 105–116.

Peer, S. (1974) “Network Analysis and Con- struction Planning.” J. Constr. Div., ASCE, 100 (CO3) 203-210.

Psarros, M. E. (1987) SYRUS: A program for repetitive projects. Master’s thesis, Dept. of Civil Engineering, Illinois Institute of Technology, Chicago, IL.

Ragsdale, C. T. (2003) “A new approach

to implementing project networks in spreadsheets.” INFORMS Transaction on Education. 3 (3) 76–85.

Reda, R. (1990). “RPM: Repetitive Project Modelling.” J. Constr. Eng. Manage., ASCE, 116 (2) 316–330.

Russell, A. D.; Caselton, W. F. (1988) “Exten- sions to Linear Scheduling Optimization.” J. Constr. Eng. Manage., ASCE, 114 (1), 36-52.

Russell, A. D.; Wong, W. C. M. (1993) “New generation of planning structures.” J. Constr. Eng. Manage., ASCE, 119 (2) 196–214.

Seal, K. C. (2001) “A generalized PERT/ CPM implementation in a spreadsheet.” INFORMS Transaction on Education. 2 (1) 16–26.

Selinger, S. (1980) “Construction Planning for Linear Projects.” J. Constr. Div., ASCE, 106 (CO2) 195-205.

Senouci, A. B.; Eldin, N. N. (1996) “Dynamic programming approach to scheduling of non-serial linear project.” J. Comput. Civ. Eng., 10 (2) 106–114.

Srigungvarl, P. (1992) “A knowledge-based integrated system for line-of-balance applications in high-rise building construction.” Doctoral thesis. Div. of Structural Engineering and Construction, Asian Institute of Technology, Bangkok, Thailand.

Stradal, O.; Cacha, J. (1982) “Time Space Scheduling Method.” J. Constr. Div., ASCE, 108 (CO3) 445-457.

Suhail, S. A.; Neale, R. H. (1994) “CPM/LOB: New methodology to integrate CPM and Line of Balance.” J. Constr. Eng. Manage., ASCE, 120 (2) 667–684.

Thabet, W. Y.; Beliveau, Y. J. (1994) “HVLS: Horizontal and Vertical Logic Scheduling for Multistory Projects.” J. Constr. Eng. Manage., ASCE, 120 (4) 875-892.

Wang, C.; Huang, Y. (1998) “Controlling ac- tivity interval times in LOB scheduling.” Constr. Manage. Econom., 16 (1) 5–16.

Whiteman, W. E.; Irwig, H. G. (1988) “Disturbance Scheduling Technique for Managing Renovation Work.” J. Constr.

book. N.-Y.: McGraw-Hill. Eng. Manage., ASCE, 114 (2) 191-213.

Downloads

Published

2022-05-20

How to Cite

Merging PDM, RSM and LSM - Scheduling Approaches into a Single Construction Project Scheduling System. (2022). The Journal of Modern Project Management, 1(2). https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/126

Similar Articles

11-20 of 431

You may also start an advanced similarity search for this article.