Merging PDM, RSM and LSM - Scheduling Approaches into a Single Construction Project Scheduling System

Pierre Bonnal
CERN Switzerland Switzerland
Mathieu Baudin
Product design and Innovation Laboratory, ENSAM ParisTech, Paris, France
Jurgen De Jonghe
CERN, Geneva, Switzerland

Abstract

There are projects for which the classical Critical Path method (CPM) or Precedence Diagramming Method (PDM) scheduling techniques are not the most suitable. Several alternative approaches have been developed over the last two decades to cope with the scheduling requirements of construction projects that are made of either repetitive activities or activities that have a linear development. Construction projects, and more specifically large-scale construction endeavors, are often composed of a mixture of repetitive activities, linear activities and more conventional project activities. The approach that is proposed in the present article enables construction practitioners to consider these three types of activities in a unique scheduling model — called Unified Project Scheduling System (UPSS) — that has a level of complexity similar to the one of CPM or PDM. UPSS has been designed so that most of the resource-constrained project scheduling algorithms can be used.

Keywords: construction project scheduling, linear scheduling method (LSM), repetitive scheduling method (RSM), unified project scheduling system (UPSS).

Information

Keywords

Project managementAgileconstructionSustainabilityproject successProjectProject SuccessDSMinnovationcase studyPMOBIMClusteringsuccessSMEDMMGovernanceLeanuncertaintyprojectcomplexityLeadershipPERTSuccessriskcriteriaschedule